COMPLETE PHASE START FINISH
Complete Concept Development & Creation of Conceptual DesignSeptember-02December-02
Complete Present Concept & Collect Feedback from College CommunityJanuary-02May-02
Complete Establishment of Budget & Economic ConstraintsMarch-02June-02
  Pursue Fundraising & Financing PlansJune-02May-04
Complete Develop Design RFQMay-02July-02
Complete Collect Design Team ProposalsAugust-02September-02
Complete Interview Prospective Design TeamsOctober-02October-02
Complete Select & Contract with Design TeamOctober-02December-02
Complete Schematic and Detailed DesignJanuary-03April-03
Complete Construction Documents & Construction BidMarch-03May-03
Complete Selection of ContractorFebruary-03May-03
Complete Pre-Construction Approvals & PermittingMay-03July-03
Complete Ceremonial GroundbreakingMay-03May-03
  Construction of BuildingJuly-03April-04
  Grand Opening & Building OccupancySummer 2004 