| COMPLETE |
PHASE |
START |
FINISH |
 |
Concept Development & Creation of Conceptual Design | September-02 | December-02 |
 |
Present Concept & Collect Feedback from College Community | January-02 | May-02 |
 |
Establishment of Budget & Economic Constraints | March-02 | June-02 |
| |
Pursue Fundraising & Financing Plans | June-02 | May-04 |
 |
Develop Design RFQ | May-02 | July-02 |
 |
Collect Design Team Proposals | August-02 | September-02 |
 |
Interview Prospective Design Teams | October-02 | October-02 |
 |
Select & Contract with Design Team | October-02 | December-02 |
 |
Schematic and Detailed Design | January-03 | April-03 |
 |
Construction Documents & Construction Bid | March-03 | May-03 |
 |
Selection of Contractor | February-03 | May-03 |
 |
Pre-Construction Approvals & Permitting | May-03 | July-03 |
 |
Ceremonial Groundbreaking | May-03 | May-03 |
| |
Construction of Building | July-03 | April-04 |
| |
Grand Opening & Building Occupancy | Summer 2004 | |